In guidelines regarding pumped-storage power producers supplying the Public Utilities Authority - Electricity, there is a chart titled מרכיבי הצמדות עלות התפעול הקבועה.

פרמטר הצמדה: חשמל
עלות תפעול בסיסית בש"ח לקוו"ט מותקן לשנה: 10.5
מטבע עדכון: ₪
ערך בסיס של מדד ההצמדה: תעו"ז מ"ע
הסבר: צריכת חשמל קבועה במתקן

kizur.co.il has תעריף עומס וזמן for תעו״ז but I still don't see how the whole phrase should be put in English. Thank you in advance!

Proposed translations

+1
23 mins
Selected

High voltage Load-and-Time tariff

מ"ע
is
מתח עליון
this is usually 161 kV, which corresponds to high voltage in the States, I believe.

The whole sentence should read:
Baseline value of the linkage index: HV Load-and-Time tariff
This means that the price is set by this tariff, plus some linkage - to the consumer price index perhaps?
Peer comment(s):

agree Moshe Devere : FYI: Taoz customer is charged lower rates for using power at off hours
1 hr
neutral meirs : Almost right - TAOZ is "TOU" (Time of Use) tariff in English - do not translate from Hebrew word for word - check the English term instead
14 hrs
Thanks !!
Something went wrong...
4 KudoZ points awarded for this answer. Comment: "Very helpful, especially for high voltage which I was having a hard time figuring out. In the end I went with "time-of-use tariff" for Taoz"
15 hrs

HV TOU Tariff

Otherwise spelled out as High Voltage Time of Uses Tariff or Time of Uses Tariff on High Voltage feed/metering.
HV means that the metering is done on the HV side infeed (161 kV in Israel) - so all the transformation losses (HV to MV, MV to LV) and any other losses in between are metered and paid for by the consumer. The compensation is that the basic per kWh rate (actually it is about MWhr) is much lower - exactly because of that.
Something went wrong...

Reference comments

15 hrs
Reference:

TOU (Time of Use) Tariff

That's the English/International term - TAOZ is a local acronym